Oct 29, 2007

U.S. Energy Department lags in meeting deadlines for securing nuclear sites

By Matthew L. Wald

WASHINGTON: More than a year after the U.S. Congress told the Energy Department to harden U.S. nuclear bomb factories and laboratories against terrorist raids, 5 of the 11 sites are certain to miss their deadlines, some by many years, the Government Accountability Office has found.

The Energy Department has put off security improvements at some sites that store plutonium because it plans to consolidate the material at central locations, but the GAO said in a Senate briefing that that project is also likely to lag. A copy of the briefing materials was provided to The New York Times by a private group, the Project on Government Oversight, which has long been pushing for better security at the weapons sites.

Danielle Brian, the group's executive director, said that although the deadline set by Congress was tight, if the Energy Department "had taken seriously consolidating and making this an expedited effort, they wouldn't be having these problems now."

Robert Alvarez, an adviser to the energy secretary in the Clinton administration, said that there was wide agreement that centralizing the fuel was a good idea. But Alvarez added, "There's a lot of pushback about moving fissile materials from a site, because then you lose a portion of your budget and prestige."

The Energy Department declined requests for an interview, but Michael Kilpatrick, a deputy chief at the department's Office of Health, Safety and Security, said in a statement that the steps under way were "further enhancements and better protection to some of the most secure facilities in the country."

But Representative Edward Markey, a Democrat from Massachusetts who has taken a particular interest in nuclear security, said in a statement, "The department seems to think that the terrorist threat to its nuclear facilities is no more serious than a Halloween prank, as evidenced by its failure - more than six years after the 9/11 attacks - to do what it must to keep our stores of nuclear-weapons-grade materials secure." Markey said the delay was unsurprising but unacceptable.

One site that will miss its deadline by years is the Oak Ridge National Laboratory in Tennessee, which holds a large stock of weapons-usable uranium. The laboratory plans to dilute the uranium, but that will take until 2015, the auditors found.

Two other sites that will miss their deadlines are operated by the National Nuclear Security Administration, which is responsible for weapons security. The agency was established in 1999 after a number of security breaches in the weapons complex, and in January its director was forced to resign because of other security lapses.

After the 9/11 attacks, the Energy Department changed its "design basis threat," the description of the attacking force against which the weapons sites should prepare their defenses. The details of this hypothetical design basis threat are classified, but the new definition specifies a larger and more capable group of attackers.

To emphasize the importance of the preparations, Congress wrote into law that the Energy Department sites should submit plans on how they would meet the requirements. Recognizing that much of the department's work runs far behind schedule, Congress specified that if a delay were necessary, it would have to be approved by the secretary or deputy secretary of energy.

An unclassified version of the Energy Department's first report to Congress, in July 2006, said that more than $420 million had been spent in the previous three years in an "aggressive" program. Among the changes was giving security officers armored vehicles and large-caliber weapons. That change reduced "the need to hire more security officers to account for the expected attrition that would be a natural result of the increased adversary force."

The department has rewritten its design basis threat several times.

Kilpatrick said in his statement that all sites now meet the 2003 version of the design basis threat and are working toward the current version, set in 2005.

The Energy Department told Congress in 2006 that six sites would meet the 2008 deadline. But the accountability office said one of those, the Oak Ridge National Laboratory, would not make the deadline.

The Energy Department said work at the five other sites would be completed later; those are the Nevada Test Site, the Hanford nuclear reservation in Washington State, the Idaho National Laboratory, the Los Alamos National Laboratory, and Y-12, a weapons site in Tennessee.

The GAO said in July that the Idaho National Laboratory would not be done until 2013, four years later than the Energy Department's estimate.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.